Balfour Beatty Rail, Inc.

Careers  |  Contact Us  |  Related Sites         
About Us | Rail Services | Transit | Projects | Partners | Media       
 
 

 Trestle Hollow Project Picture

SCTRA -- Trestle Hollow

Client/Owner: South Central Tennessee Railroad Authority
Project Start Date: May 2008
Project Completion Date: October 2008

Balfour Beatty Rail, Inc. built new track using 115# jointed rail on M-10 steel ties. The team also constructed two road crossings, surfaced and aligned about 6,800 feet, and removed 4,800 feet of existing track.    
 
 

   © 2009-2010 Balfour Beatty Rail, Inc. All rights reserved.
Home  |   Safety  |   Sustainability  |   Site Map